Golden Pass LNG
Golden Pass LNG

Owner:
Golden Pass LNG

Client:
CB & I Constructors

Location:
Sabine Pass, TX

Size:
120,000 cy

Schedule:
Jan. 2006 - Jun. 2009

Project Details

Located in Sabine Pass, Texas, Golden Pass LNG Terminal was developed to meet the rising demand for an energy source that is safe, long-term, and dependable. Once completed, the Golden Pass LNG project plans to import LNG to provide about two billion cubic feet per day.  Baker's contract consisted of a total package containing five complete LNG containment tanks, slabs, walls, and concrete roofs.